Quick answer
A site is ready for a kitchen install when the walls are lined and stopped with at least a first coat of paint, the flooring decision is made and done if it goes under the cabinets, plumbing and electrical are roughed in where they will stay, and the install team has clear access, power and an empty room. If any one of those is missing, the crew either can't start or fits cabinets that will need coming back to.
Key points
- Linings stopped and sanded, with at least a first coat of paint where the cabinets go.
- Decide the flooring before the measure: under the cabinets, or up to the kickboard.
- Water, waste, gas and power roughed in by licensed trades, and not moving after we measure.
- Clear access from the street to the room, somewhere to park and unload, and working power.
- An empty, swept room and a named person on site who can answer questions.
- Builders send a trade request with no fee; homeowners book a free measure & quote.
Every builder has had the day where the joinery turns up and the room isn't ready for it. The stopper is still working, the floor layer is halfway through, or the plumber has decided the waste would be better a little further along. Getting the site ready for kitchen install is the cheapest thing you can do to keep the cabinets on programme, and it's mostly a matter of ticking off a short list before you confirm the date.
This checklist is written for a single home build or a large renovation, where you're running one site and want the joinery to go in on the first visit. For the wider question of where the kitchen sits in your programme, our guide to coordinating the kitchen install with your other trades covers the full sequence. This one is the go or no-go list for the room itself.
Why a ready site matters more than a fast one
Cabinets are built to the measurements we took on site. If the room has changed since then, or isn't finished enough to fix to, the install slows down or stops. A crew that has to work around a wet wall, a missing floor or a moved pipe can still get cabinets in, but they'll be fitted to a room that isn't final, and that is where gaps, out-of-level runs and return visits come from.
A ready site also protects the joinery. New cabinets sitting in a room where sanding, plastering or floor sealing is still going on pick up dust in the drawers, scuffs on the doors and moisture in the board. Our carcasses are 18 mm moisture-resistant board, which helps, but no board is meant to sit in a room that's still drying out.
A ready room is worth more to the programme than an early install date.
Linings, stopping and paint
The walls the cabinets fix to need to be lined, stopped and sanded. Cabinets screw back through the linings into framing or dwangs, so the linings have to be on and the fixings behind them where we expect. If you've planned extra dwangs for wall cabinets or tall units, make sure they went in before the linings did. It's a common thing to miss on a new build.
Paint is the other half. Most builders get at least a first coat on before the cabinets go in, so the painter isn't cutting in around fresh joinery and dripping on new benchtops. The final coat can follow the install if that suits your painter, but agree that before the day. Splashback tiling, glass or panels come after the cabinets and benchtops are fixed.
The flooring decision
Flooring is the item most likely to hold up an install, because it's often decided late. There are two common approaches. Either the floor runs under the cabinets, so it's laid before we arrive, or the cabinets sit on the subfloor and the flooring runs up to the kickboard afterwards. Both can work. What matters is that the decision is made before we measure, because it changes the cabinet heights, the benchtop height and how the kickboards are fitted.
Floating floors such as laminate or some vinyl planks often have their own rules about heavy, fixed items sitting on them, so check the flooring manufacturer's instructions before deciding. Tiles are usually laid before the cabinets, with care taken over the height difference at the appliance gaps. Whatever you choose, tell us at the measure, not on install day.
| Approach | What it means for the install | What to check |
|---|---|---|
| Floor under the cabinets | Floor laid and protected before we arrive; cabinets sit on the finished floor | Floor protection is down, and the flooring maker allows fixed cabinets on top |
| Floor up to the kickboard | Cabinets fixed to the subfloor; flooring laid afterwards | Finished floor height is known so the kickboard and dishwasher gap still fit |
| Tiles | Usually laid before the cabinets | Tile height at the dishwasher and oven gaps |
| Undecided | We can't confirm heights | Make the call before the measure |
Services roughed in and staying put
Water supply, waste, gas and electrical outlets need to be roughed in by your licensed plumber, gasfitter and electrician before we measure, in the positions they'll finish in. Our cabinets are cut around those positions. A waste that moves along the wall after the measure can mean a new cabinet back or a new end panel, and that's a delay nobody needs.
The things we look for on the walls: the sink waste and water points inside the sink cabinet footprint, a power point for the dishwasher and the rangehood where the plan shows them, the oven and cooktop supply ready for the electrician or gasfitter to connect later, and nothing poking out where a cabinet side or a drawer runner needs to go. Our earlier piece on site measure vs plan measure explains why we build to the real walls rather than the drawings.
Access, parking and a path to the room
Our cabinets arrive assembled, not flat-pack, which saves a lot of site time but means bigger pieces coming through the door. A tall pantry or a long benchtop needs a clear path from the truck to the room. Check the route for scaffolding, stacked materials, tight turns on stairs and doorways with no door hung yet.
Parking matters on Auckland sites more than most. A narrow street, a shared driveway or a site with a skip and three utes already on it can turn unloading into a long job. Let us know about anything awkward ahead of time: steep drives, rear sites, long carries, or a neighbour's driveway that mustn't be blocked.
- A clear route. No materials stacked in hallways or on the stairs the cabinets need to come up.
- Somewhere to unload. A spot for the truck close to the house, kept free on the day.
- Doors and openings. Know the narrowest opening on the route; tell us if a door frame is going in later.
- Lockable or watched. If the site isn't secure overnight, tell us, so we can plan the delivery around it.
Power, light and a clear room
The install team needs working power for tools in or near the room, either the house's own outlets or a temporary supply your electrician has set up. Decent light matters too. Fitting cabinets in a dark room with one bulb hanging from the ceiling is slower and less accurate, so if the lighting isn't in yet, tell us beforehand and arrange temporary lights.
The room should be empty and swept. That means no offcuts of plasterboard, no paint tins along the wall the cabinets go on, and no other trade working in the same space that day. Two crews in one small kitchen is a recipe for damage and for both jobs taking longer.
What our install team needs on the day
On the morning, the install team needs to know who to talk to. Give us the name of someone on site, or a phone number for someone who can answer questions and make decisions. Most days nothing comes up, but if something does, a quick answer keeps the crew working instead of waiting.
Before you confirm the date, run through this list. If any line is a no, it's better to move the install than to start it on an unready room. Our article on how to avoid kitchen install delays goes through the wider causes of slipped dates.
| Check | Ready when |
|---|---|
| Linings | Lined, stopped and sanded where the cabinets go |
| Paint | At least a first coat on the walls behind and around the cabinets |
| Flooring | Decided, and laid and protected if it goes under the cabinets |
| Services | Water, waste, gas and power roughed in, unchanged since the measure |
| Fixings | Dwangs in place for wall cabinets and tall units |
| Access | Clear route, door openings known, somewhere to unload |
| Power and light | Working outlets or temporary supply in or near the room |
| Room | Empty, swept, no other trade in it that day |
| Contact | A named person on site or reachable by phone |
After the cabinets: who comes next
Once the cabinets, benchtops and doors are in, the room goes back to your trades. The plumber connects the sink, tap, waste and dishwasher, the electrician or gasfitter connects the oven, cooktop and rangehood, and the tiler does the splashback. If the floor runs up to the kickboard, the floor layer comes in, and then the kickboards go on. The painter's final coat fits wherever you've agreed.
Our install team works from our East Tāmaki workshop and installs what we make, so if anything isn't right with the cabinetry after the trades have been through, there's one business to call. The cabinetry carries a 10-year warranty.
Frequently asked questions
Should flooring go down before or after kitchen cabinets?
Either can work. What matters is deciding before the measure, because it changes the cabinet and benchtop heights and how the kickboards fit. For floating floors, check the flooring maker's instructions about fixed cabinets.
Do walls need to be painted before the kitchen is installed?
Most builders put at least a first coat on first, so the painter isn't cutting in around new joinery. The final coat can follow if you agree that with the painter beforehand.
What does a kitchen installer need on site?
Lined and stopped walls, services roughed in where they'll stay, a decided floor, clear access from the street, working power and light, an empty room and a person who can answer questions.
Can the plumber and electrician work at the same time as the kitchen install?
It's better not to share the room. Licensed trades rough in before we measure and connect after the cabinets and benchtops are fixed, which keeps each job clean and quick.
What happens if the site isn't ready on install day?
The crew may not be able to start, or would be fitting cabinets to a room that isn't final. It's usually better to move the date than to install into an unready room, so run the checklist before confirming.
Book the joinery for your build
Builders and developers can send us a trade request with no fee, and we'll talk through your site and the stage it's at. Homeowners running their own renovation can book a free measure & quote: it's GST included, we measure everything on site and send a detailed quote.