New Floor Before or After the Kitchen Goes In?

By the MTN Kitchens workshop team · East Tamaki, Auckland · 2026-11-26 · 9 min read

23+ years' trade experience · 2,000+ kitchens supplied & installed across Auckland · Laminex NZ fabricator

Should the floor go down before or after the kitchen? Flooring under or up to cabinets for vinyl, tiles, timber and carpet, appliance heights and sequencing.

Quick answer

Whether the floor goes before or after the kitchen depends on the flooring. Tiles and glued-down vinyl usually go in first and run under the cabinets, while floating floors and carpet usually go in after and stop at the kickboard line. Either way, the floor must be finished under the dishwasher, fridge and oven spaces, so decide the order with your flooring layer before the kitchen is measured.

Key points

  • There are two sound methods: the floor runs under the cabinets, or the kitchen goes in first and the floor runs up to it.
  • Floating floors generally shouldn't be pinned down under fixed cabinets. Check the flooring maker's instructions.
  • Appliance spaces need the finished floor in place whichever method you choose, or the dishwasher may not fit under the bench.
  • Kickboards are fitted last, to the finished floor, so the order changes who comes back when.
  • Tell us the floor plan at the measure: the free measure & quote is when we set heights to suit it.

When a kitchen and a floor are both being replaced, someone always asks: floor before or after kitchen? The flooring layer may have one view, the kitchen company another, and you are the one paying for both. Get it wrong and you can end up with a dishwasher that won't slide in, a gap along the kickboards, or new flooring scratched by an install crew.

The good news is that both orders work when they are planned. What matters is choosing one before the kitchen is measured and telling every trade. This guide covers the two methods, what each floor type prefers, the appliance heights that catch people out, and how to sequence the flooring trade around the install.

Two ways to do it: under the cabinets or up to them

Floor first. The new floor is laid across the whole room, and the cabinets are installed on top of it. The floor runs continuously under the base units.

Kitchen first. The cabinets go onto the subfloor, and the new floor is laid afterwards, stopping at the line where the kickboards will sit. The kickboards then go on to cover the edge.

The two methods compared
Floor first, under cabinetsKitchen first, floor up to kickboards
Flooring usedMore, because it covers the area under the unitsLess, the floor stops at the kickboard line
Future layout changesEasy: the floor is already there if a cabinet movesHarder: moving a cabinet exposes a gap in the floor
Risk to new floorNeeds protecting during the installLaid after the install, so less exposure to the crew
SuitsTiles, glued vinyl, sheet vinylFloating floors, carpet in open-plan spaces
Appliance spacesFinished floor already thereFloor must still run into each appliance space

Laying the floor first, under the cabinets

This is the tidier long-term result. The floor is one continuous surface, so if you later swap a cabinet for a dishwasher, move a pantry or change the layout, there is no patch to explain. Water that gets past a kickboard lands on finished flooring rather than bare particleboard subfloor.

The costs are more flooring material and a finished floor that has to survive install day. Cabinets, benchtops and tools are heavy, so the flooring layer or the install team needs to cover the floor with protection along the work area and the carry route. The cabinets also stand on their adjustable legs on the new surface, so a floor that isn't level still needs the legs set carefully.

Fitting the kitchen first, floor up to the kickboards

Here the cabinets are levelled on the subfloor, and the new floor comes in afterwards. It uses less material and keeps the new surface away from the heaviest part of the job. It is the usual approach where the floor is a floating type that needs to move freely.

The trade-off is flexibility. The area under the units has no new floor, so any future change to the cabinet layout means patching. The kickboards also have to wait until the floor is down, which means a return visit to fit them, and the flooring edge has to be cut neatly along the cabinet line so the kickboard covers it.

Vinyl, tiles, timber and carpet: what each one prefers

The flooring type usually decides the method. These are general patterns; the flooring maker's installation instructions and your flooring layer have the final say.

Sheet vinyl and glue-down vinyl

Glued to the subfloor, so it doesn't move and can sit under cabinets without trouble. Many rental and family kitchens use it for that reason. Laying it first gives a sealed, continuous surface under the units.

Floating vinyl plank and laminate

These click together and float, so they need room to expand and contract. Pinning them down under heavy fixed cabinets can stop that movement and cause gaps or lifting elsewhere. Most floating floors go in after the kitchen and stop at the kickboard line, with an expansion gap the kickboard hides. Check the maker's instructions, because some products allow otherwise.

Tiles

Tiles are rigid and fixed, and they are often laid first so the cabinets sit on a finished surface. Laying them under the units costs more tile and labour but avoids a cut edge at the kickboard. If tiles stop at the cabinets, the edge must be neat and the tiles still need to run into the appliance spaces.

Timber

Solid timber nailed or glued to the subfloor can run under cabinets, though some owners stop it at the kickboard to save material. Engineered timber is often floating, and behaves like a floating plank. In both cases the timber is at its best when it isn't sitting in water, so a well-sealed sink cabinet matters.

Carpet

Carpet doesn't belong under kitchen cabinets. In an open-plan room it usually goes in last and meets the kitchen floor at a transition strip somewhere clear of the bench.

Appliance spaces need the finished floor either way

This is where most of the trouble comes from. A dishwasher is designed to slide into a set height under the benchtop, measured from the floor it stands on. If the cabinets go in on the subfloor and new flooring is then laid into the dishwasher space, the floor rises and the gap under the bench shrinks. A dishwasher that fitted on paper may not go in, or may only go in with its feet wound right down.

The same applies to a freestanding oven, which is built to line up with the bench height. Our article on getting a freestanding oven gap right explains how the bench line and the floor work together. A fridge space with a wall unit above it can also lose height if a thick floor goes in afterwards.

The fix is simple: we set the cabinet heights to the finished floor level, not the subfloor. That means we need to know what floor is going in and how thick it is with any underlay, before we measure. If you are adding a dishwasher to an existing kitchen, the same check applies to the floor in that space.

Sequencing the flooring trade and the kitchen install

Most renovations follow one of two running orders. Pick the one that matches your floor, then share it with your flooring layer and us.

  • Floor first. Strip out, subfloor repairs, plumbing and electrical rough-in, floor laid and protected, kitchen installed, benchtop and splashback, kickboards fitted to the finished floor, appliances in.
  • Kitchen first. Strip out, subfloor repairs, plumbing and electrical rough-in, kitchen installed and levelled, benchtop and splashback, floor laid up to the kickboard line and into appliance spaces, kickboards fitted, appliances in.

In both, kickboards go on last because they are scribed to the finished floor. If you are coordinating a bigger job, our guide to coordinating a kitchen install with other trades is written for builders running several units, but the order of trades it describes is the same idea at a larger scale.

Pick the floor before we measure, and the heights take care of themselves.

Renovations: when the old floor stays, goes or gets patched

Not every kitchen replacement comes with a new floor. When the old floor stays, the new cabinets often have a different footprint, which can leave unfloored strips where old units used to sit. Look at the plan and ask where the new cabinets end compared with the old ones. A slightly longer run can cover a gap; a shorter one can expose one.

Strip-out also reveals what the old kitchen hid. Swollen particleboard flooring under an old sink is common in Auckland houses, and it needs repair before anything new goes on top. In older houses, old vinyl and its backing can contain asbestos, so have it tested before anyone lifts or sands it, and follow WorkSafe's guidance on what to do if it is positive.

If you will be living in the house through the work, the order also affects how long the kitchen area is out of use. Our article on living at home during a kitchen replacement covers what goes offline and when.

What to tell us at the measure

The measure is the moment the floor decision turns into cabinet heights. Have these answers ready:

  • The floor type and product. Vinyl, tile, timber or carpet, and whether it floats or is fixed.
  • The finished thickness. Including any underlay or levelling compound.
  • The order. Floor first or kitchen first, agreed with your flooring layer.
  • The appliances. Their models and sizes, so the spaces are right for the finished floor.
  • The subfloor. Anything you already know about soft spots, slopes or old water damage.

If you want a price before booking anything, bring photos, wall-to-wall measurements, the appliances and a note on the flooring to our East Tāmaki shop for a free quote at the shop. If you would like us at the property, our free measure & quote, covers a full measure on site and a detailed quote.

Frequently asked questions

Should I put the flooring down before installing kitchen cabinets?

It depends on the floor. Tiles and glued vinyl usually go down first and run under the cabinets; floating floors and carpet usually go in after and stop at the kickboard line. Either way, decide before the kitchen is measured.

Can you put a floating floor under kitchen cabinets?

Usually not, because heavy fixed cabinets can stop a floating floor moving as it should. Most floating floors are laid after the kitchen, but check the flooring maker's installation instructions for your product.

Do kitchen cabinets go on top of tiles?

They often do. Laying tiles first gives the cabinets a finished, level surface and avoids a cut tile edge at the kickboards, though it uses more tile.

Will a new floor stop my dishwasher fitting under the bench?

It can, if the floor goes into the dishwasher space after the cabinets are set to the old floor level. Tell your kitchen maker the finished floor thickness so the cabinet heights allow for it.

Who fits the kickboards if the floor goes in after the kitchen?

The kitchen installer usually fits them once the floor is down, scribed to the finished surface. Plan that return visit into the order of work.

Get the heights right from the start

We build our cabinets in our East Tāmaki workshop and fit them with our own install team, set to your finished floor. When you know what floor is going in, book a free measure & quote and we will measure, check the appliance spaces and send a detailed quote. Rather not pay for a visit? Bring photos and a few measurements to our East Tāmaki shop and walk away with a free quote on the spot.